Week by week watch Longtree rise! Welcome to Longtree

 
Home
....................
Longtree completed!
A dream comes true
Owners raced the snows
in rush to make deadline
....................
Tasteful Companies
Make Longtree
A Special Home
....................
What They Say
About Longtree
Unusual...dramatic...unique
....................
Ancient Secrets of An Old-Growth Forest
Petrified wood ... a governor
....................
Longtree's Origin:
Wild & Untamed
Pine tree giants abound;
voices from another time
....................
The Architect
Behind Longtree
Meet Robert A. Armon
....................
Built Green
Exacting standards
....................
Contact

The building of Longtree;
21 months, start to finish
May | June | August | November | March

Colorado's weather cooperated and the first three months of 2005 were generally mild, with scattered snow showers. The builders of Longtree (R. D. Simmermon & Company, Inc.) took full advantage. Grading and excavation by Multi-Contractors of Denver began on Jan. 14, 2005. The 13-foot-deep basement had been dug out and the first footings poured by Jan. 24, by JAJ Concrete.

Most of the basement and upper story walls were poured by Feb. 14. Various retaining walls and bracing walls were poured by Feb. 25, as were footings for the bedroom tower and four-car garage.

Framers (Eagle Eye Construction) went to work on March 7. By March 11

the main floor was laid, and several wall sections and steel were in place by March 18. The library, Robin's office, exercise room, breakfast room and kitchen area were formed by March 30.

The home continued to rise in early April. John's office and the master bedroom tower (with individual his & hers closets & baths) was framed in by April 8. But on Sunday, April 10, look out! The Denver metro area was hit by a fierce blizzard that brought the city and the Denver International Airport to a halt. Longtree was barraged with 2 1/2 feet of snow. But the weather warmed almost immediately and by April 14 the floor for the outside upper deck had been completed.

Construction will slow until trusses are delivered in May.

May, 2005 construction update

Trusses arrived in early May and work resumed at a frenzied pace--first over the garage, then over the morning room just off the kitchen. In the second week of May a crane lifted trusses one-by-one to the third story roof line where framers secured them in position. In two days they had completed most of the job.

Framers from Eagle Eye Construction completed work on the stairway that wraps around the elevator shaft from the basement up to Longview, the fourth story viewroom, high atop the structure. For the first time Robin and John stood on the floor of Longview and could see Pike's Peak, the Rockies and a pastoral landscape that stretched in a huge 3/4 arc before them with an estimated viewing distance of 70 miles. This will be the hit room of the home.

Heir Drilling company dug Longview's well in one day (May 18) and it tested out with enough pressure to pump 100 gallons a minute. That was more than enough because we are allowed to pump only 15 a minute. Well depth was 477 feet. The well was "Static" (depth to which the pressure forced up the water) at 230 feet. The "Draw down" (depth to which the water dropped after baling tests at 15 gallons per minute) was 260 feet. "Awesome!" said Bruce Heir.

The large pentagon roof on John's office went on two days later. The pentagon roof on the master bedroom was in place by May 23. Work is continuing on Longview. Side walls that will house huge vertical Pella windows were in place at the end of the month.

The weather has turned warm, with temperatures as high as 90.

Top


June 1 to July 12, 2005, construction update

Warm, mostly clear weather in early June allowed framers to move quickly to put the roof on the towering view room (Longview) and to begin to attach the fascia on all under-roof areas of the home. Afternoon thunderstorms hampered work in mid to late June but did not delay construction of the 5-stop elevator shaft. Rubberized plastic sheeting was applied to all roof areas by late June, and the third story deck was completed and ready for its concrete floor by June 23.

Installing of the 5-ton, pentagon-shaped skylight drew crowds of photographers in late June. The huge steel frame was assembled and welded on site, then lifted by crane to its third story resting place. Workers guided the frame into place and bolted it to ledges designed to support it. Twin steel beams were installed to steady portions of the frame that juts out over the third story deck.

Pella experts led by Doc Tully began to install Longtree's 119 windows in early July. Since some installations took place nearly 65 feet above ground level, Tully called in a crane to assist. Installers work on one window at a time--one of them outside on an extension ladder, the other inside. Most of the work was completed by June 12.

The prow-shaped roof over the main entrance was completed by July 7. Temperatures soared into the mid-90s, typical for this time of the year in Colorado. Because of heavy spring rainfall, the land around Longtree continued to teem with native grasses and wildflowers.

Top


July 13 to September 1, 2005, construction update

With the installation of windows finished and framing about 95% complete, much of the work during the warm midsummer period turned to the inside of the home. Lance Graham and his crew from Precision Plumbing began the installation of water pipes and drains in late July.

Especially interesting was the installation of piping inside the elevator shaft, soaring from the basement to the floor of Longview. Lance made it look easy. And since water pipes underneath the bridges between the center home and the two towers will be exposed to freezing temperatures, arrangements were made to pipe in heat to protect them. Most of the rough plumbing was in by Sept. 1.

Four Seasons Heating & Cooling began its preliminary work in August. "Tinners" led by Dan

Maul assembled from scratch the heating and air conditioning ducts that will feed every room in the home. One large duct zooms up the elevator shaft next to plumbing pipes. By Sept. 1, their work was about 70% completed.

A new crew appeared in late July and began to double wrap the outside of the building with black "felt" preliminary to stone and stucco. By early September they had covered the "felt" with supporting wire and were about ready to begin the application of stone and stucco (the stone will be dark, the stucco a dark green to make the building blend into the forest that surrounds it).

Chilly nights and turning leaves marked the beginning of September. The forecast is for an early winter.

Top


Sept. 2 to December 7, 2005, Construction Update

The installation of Longtree's heating and air conditioning systems continued. The home will include four G61 furnaces and three Lennox HSX15 air conditioners, all from the Dave Lennox Signature Collection.

In October, a smiling gentleman named Merlyn Discua, of Arapahoe Fire Protection, began the installation of Longtree's sprinkler system. And if you zoom down to row 26 on the week-by-week picture page, you'll see him demonstrating his dazzler.

Later in the month, the Romeros decided to cut back the tall, ship-like prow atop Longview, the fourth story viewing room. The move took several feet off Longview's height without altering the interior. A powder room was added to Longview as well.

Also in October, the home's Waupaca elevator was delivered by the Certified Elevator Company, Inc., of Centennial, CO. Certified's owner Tony Mateyko says his men will begin assembling the cab inside the elevator shaft early in 2006.

Stucco work was delayed by the alteration to Longview, but will resume in December, weather permitting. The Romeros chose a forest green stucco color, accented by dark stones on the lower elevations of the home and towers.

The installation of contrasting brown shingles began in late November, and was expected to be completed by late December.

Snowstorms? We had a wicked one in October. It hit before the trees had shed their leaves and resulted in widespread damage in metro Denver. The wet, heavy snow that measured two feet deep and more caused a number of broken branches.

We were nailed again in late November with a combination of snowfall and very cold weather. This time the trees survived, but the overnight in metro Denver was -4, and the high on Dec. 7 was 11. The storms and cold delayed work on Longtree by two to three weeks.

Merry Christmas to all, and to all a good year.

Top


December 8, 2005, to March 31, 2006

Most of Longtree's electric work was completed in early March, by a crew from Endeavor Electric led by Mike Drinkard. The home has two mechanical rooms, each with two panels.

In February, Acoustic Visions of Boulder, CO, began installing low voltage wiring with a team that included Kyle Novak, Bazil Baldwin and Adam Weisgerber. Longtree will have eight HDTV sets of varying sizes (some are flat screen swing-out wall mounts, two of which are in the kitchen) plus numerous dedicated telephone lines. Acoustic Visions also will install a home theater in the basement entertainment center. .

A pump and two large cisterns were installed by Arapahoe Fire Protection to serve the array of overhead sprinklers throughout the house. A lightning protection system consisting of copper spikes placed strategically on various roof sections and a heavy copper wire that connects them was in place by the end of March.

Stucco application went slowly because of intermittent snow and cold and a custom texture change from lumps and bumps to a smoother, more wavelike surface. The dark green color blends beautifully with forest surroundings and virtually makes the home disappear when seen from a distance.

Colorado Plastering completed most of the stucco and began application of cultured stone as March ended. The stone, although multicolored, has a dark appearance that meshes with the stucco color and the surrounding forest.

A double leach field northwest of the house was completed in February. It was covered over and made ready for use when the home is occupied.

Millwork under the direction of Randy Wade Millwork began on the home's large main entrance and various interior doors. The front door will feature two rows of clavos (large metal studs) which will be picked up by key interior doors.

Quick Hits: Work began on the entertainment center pub...the larger of two guest suites was outfitted with a corner tub and ceiling-mounted rainfall shower...the entrance to the library was custom built by Nate Latimer to mimic the home's soaring main entrance...Robin and John chose bronze-colored All American Rolling Shutters for various windows...insulation and drywall work are due to start in April.

Sure looks like a beautiful Spring.

Top


April 1 to October 6, 2006 Construction Update

Robin steps up
makes decisions that bring Longtree in on time

     March to October sounds like a long time. It isn’t when your dream home is rapidly coming together and there are hundreds of last minute decisions to make. We had good weather most of the way, so that helped.

     We also had Robin, who stepped up (a little sports jargon, there) and took charge of selecting interior and exterior lighting, tile, carpeting, interior room colors and kitchen decor. Come to think of it, that’s about everything we had left to do.

     Robin’s work was made easier by designer Lyn Bartels, an executive of the contractor and a close friend. Her expert guidance and knowledge in both interior and exterior design saved us time and error.

     The granite top kitchen counters and island, for example, came from a showroom that Lyn recommended. She and Robin checked out the inventory and Robin settled on Vyara, a beautiful varicolored stone. Robin had an idea to use the serried edges of the original slab as the back splash. The striking finished product looks like the distant Rocky Mountains.

     Robin chose three different carpets--one for most of the home, a second for the basement only and a third for the stairway. She then selected eight different rooms colors (most will be shown on the week-by-week pictorial record of Longtree).

     Friend Tony Mateyko, owner of Certified Elevator in Denver, installed a beautiful. five stop Waupaca elevator. Near the completion of construction, Acoustic Visions of Boulder, CO, ran low voltage wiring and installed the various television sets and speakers.

     Project Manager Ron Schauman said he could bring the home in by October, and did it. Without Ron’s knowledge of every facet of homebuilding, we’d never have made it.

     The kitchen appliances came from a number of brands--our favorite being a Meile Steam Oven that can cook three foods at once One of the last projects was “Bailey’s Yard,” a grass-covered courtyard in the center of the home for Robin and John’s Basset Hound, Bailey. Another beautiful final touch was added by Nick Latimer, owner of Latimer Construction, who installed cedar wood at the top of the iron pentagon, under the third story deck and under other extensions.

     Racing the snow, we moved into Longtree in mid-October. Unfortunately, we didn‘t win. John moved his computer and office machines to the home a week in advance of the furniture move and would have been snowed in his second day if not for a neighbor who plowed the driveway so he could escape.

     So Longtree was completed. Well, almost. Landscaping still remains to be done, along with the labyrinth. And there are about 3,000 old growth Ponderosas that need trimming. So stay tuned. We’ll be telling you (and showing you) about Longtree as it develops over the next two years.

     

Top

Architecture and the quality of life

I think people are realizing that Architecture...has a lot to do with the quality of your life.

--Architect Daniel Libeskind, selected to create a master plan for the
World Trade Center in New York, and the man who designed the Denver Art
Museum and the adjacent Museum Condos, as quoted in the Denver Post